
8 Week Delivery Timeline
180 FEEDERS COMPLETED
5 FEEDERS COMPLETED
95% DONE WITH NETWORK TRACES
800K UN CONDITIONS REDUCED TO ZERO
80% ACCURACY ON AGAT MAPPING
Week 1
Week 2
WEEK 3-4
WEEK 6
WEEK 7–8
Week 1
Mapping decided in 3 hrs
AI-generated AGAT recommendations were ~80% right out of the gate; Cobb finalized mapping in 3 working sessions.
Week 2
Initial dataset migrated
800,000 UN validation conditions reduced to almost zero in 2 weeks by rule and configuration changes.
WEEK 3–4
Tracing functional
All five client-selected subnetworks traced successfully and clear of dirty areas, on >1.4M generated associations.
Week 6
Remediation & data accepted
Built revised scripts with AI and fixed all remaining geometric data issues. Final POC data submitted and accepted.
WEEK 7-8
180 feeders completed
Mappings, configuration, and scripts from POC reused to migrate 180 additional feeders to UN in 2 weeks.
